Stalled Development in the 39th Council District

We need to make these sites into assets for the community. Many of these developments are causing real hazards for their neighbors, with fences falling down on sidewalks, loose construction debris that can become deadly in high winds, and unsecured sites that are dangerous for children and an invitation to squatting.

Help the effort to convert local blight to community benefit by providing feedback and tracking the progress of each site.
Leave comments below on a individual site to update us on the conditions. If you call 311 about an issue, please leave a complaint number in the comment.

Sunday, March 14, 2010

277 1st Street, Park Slope


(between 4th Avenue & 5th Avenue)

Blog reader addition!

Project Type: New Building

Project Description: Originally planned a 4 story 2 unit building (1999); new plan for a 4 story 5 unit building (2002)

Status: Building Infrastructure Partially Complete

Background: This project was initiated in 1999 but was significantly expanded in 2003. The 1999 plan was for a new 4 story, 2 unit, 4,000 sf building. The plans were withdrawn in 2003 and new plans were filed to build a 4 story, 14,000 sf building by merging adjacent lots. The plans refer to 3 units, but they may mean 3 units per original lot, thus totaling 9 units.

The Park Slope Rezoning halted work, but the DOB determined that it was sufficiently far along to proceed under the previous rules.

There have been several major safety violations:

- 2004: In May a violation was issued for failure to protect public and property affected by construction operations. The violation noted that one side of the excavation fence and a portion of the side yard had collapsed due to improper sheeting and shoring of the excavation and foundation. In June a violation was issued for failure to provide protection of sides of an excavation approximately 15 feet long in front of the building. In November a violation was issued for failure to provide protection at the side of excavation. Protection was not provided, and along one wall there was no sheeting, shoring or bracing. A Stop Work Order was issued.

- 2005: In May a violation was issued for work contrary to approved DOB plans; a crane was hoisting steel in the wrong position. The contractor also failed to have a permit signed off by an engineer. In December a violation was issued due to the lack of a sidewalk shed. The inspector noted that steel framing for the new building of approximately 50 feet in height had been erected without a sidewalk shed for protection of pedestrians on sidewalk. A Stop Work Order was issued.

- 2007: In March a violation was issued because the sidewalk shed did not meet building code specifications. The shed was missing lighting and a deck enclosure.

- 2008: In February a violation was issued for lack of guardrails along an opening on the roof terrace.

- 2010: In February another violation was issued because the sidewalk shed did not meet DOB code requirements. It was missing a parapet on the top of shed.

Permits are still active.

The building has 4 full floors and a fifth floor that may be a terrace or other structure.

No comments:

Post a Comment